Court Street renewal work set this month

DALLAS -- Work will begin next week on the Dallas Urban Renewal District's Streetscape project on the south side of the 100 block of Southwest Court Street.

DALLAS -- Work will begin next week on the Dallas Urban Renewal District's Streetscape project on the south side of the 100 block of Southwest Court Street.

A construction plan is set to follow this preliminary schedule:

* Sidewalk demolition -- Monday, Sept. 12, through Thursday, Sept. 15

* Site preparation and installation of new sidewalk -- Sept. 20-23.

* Site preparation and installation of new curb -- Sept. 26-28.

* Installation of pervious concrete and pavers and cleanup -- Sept. 29-Oct.13.

Court Street businesses in the construction zone will be open during work, with minimal interruption of parking and pedestrian access.

For more information: 503-831-3565.